The challenge
Driving up a mountain with a rotor blade
Prangl was commissioned with transporting wind energy components for the new Bärofen wind farm in Carinthia. The facilities are located at an elevation of approx. 1,630 metres and should be in operation as early as the first quarter of 2027. The journey to the construction site was particularly challenging due to the tight corners and steep gradients.
Our solution

Delivery concept
Prangl was commissioned with transporting wind energy components for the new Bärofen wind farm in Carinthia. The facilities are located at an elevation of approx. 1,630 metres and should be in operation as early as the first quarter of 2027. The journey to the construction site was particularly challenging due to the tight corners and steep gradients.

Rotor length of 68.6 metres
With its length of 68.62 metres, a maximum width of 3.92 metres and a maximum height of 3.35 metres, the blades were a particularly tricky cargo. The weight of nearly 24 tons is also no small matter. The rotors were, as with all the other components, delivered from the port of Bremen to a specially developed transfer point in Deutschlandsberg. From there, they were sent up the mountain. The most important device was the unique blade transport device. It is extremely flexible due to an adapter flange, which allows all types of blades to be transported.

35 kilometres uphill
Transport weights and some very steep mountain roads were the reason for choosing a 8x6 semi-low-loader from the Prangl fleet. And that's not all. In order to overcome the steepest inclines, a second semi-low-loader was also used. And so the thoroughly prepared convoy set out, rotor by rotor, on an arduous journey, which totalled 35 kilometres. The route initially followed an asphalt road, which later turned into a reinforced forest track. Whenever the incline became too steep, a second tractor was hitched up, making it possible to negotiate all the steep sections without any trouble.

Flexible blade transport device
In the tight corners, the blade transport device made the most of its big advantage: By positioning the rotor upright, it was possible to navigate even the tightest corners, including those in wooded sections, without risking any damage to the valuable blade. Where power lines spanned the road, the blade was moved into a horizontal position. In this way, after a journey uphill lasting around 5 hours each, all the rotors were transported, one by one, to their respective destinations within the Bärofen wind farm, where green energy will soon flow ...